Services and panels
What you’ll learn
- The path from the utility transformer through the meter and the main disconnect to the panel.
- Why a 120/240 V service gives you 120 V and 240 V, and what the neutral carries.
- The one place neutral and ground are joined, and why subpanels keep them apart.
- Which parts of a panel stay live with the main off.
A service is everything between the utility’s wires and the first overcurrent device in the building: the service conductors, the meter, the main disconnect, and the panel it feeds. This lesson follows the power from the pole (or the pad) to a branch circuit, names each part, and explains the two ideas that trip people up: what the neutral actually carries, and the one place it is joined to ground. How big any of it must be is a code-book question; how it works is here.
From the utility to the panel
The utility transformer (on a pole, or a green box on a pad) steps the distribution voltage down to what the building uses. The service conductors come from there, overhead (a service drop to a mast) or underground (a service lateral), to the meter, which only measures energy. Next is the main disconnect — usually the main breaker at the top of the panel, sometimes a separate switch — the one place you can switch off everything the service feeds. Then the panel: busbars that the branch-circuit breakers clip onto, a neutral bar, and a bar for the bonding conductors.
Who owns what varies: in most places the utility owns everything up to the meter, and you own from the meter base on. Your utility’s service guide and your code book both have a say in the service; find out which rules your area follows before you plan one.
120/240 V split-phase
A house service in Canada and the US is usually 120/240 V single-phase. The transformer’s secondary is one winding with a tap in the middle. The two ends are L1 and L2; the middle is the neutral. From either end to the middle is 120 V; from end to end is 240 V. Each row of breaker spaces down the panel is on the opposite line from the row above it (the left and right spaces in one row share a line), so a single-pole breaker gives you 120 V and a double-pole breaker, straddling both, gives you 240 V.
Seen from the neutral, L1 and L2 point opposite ways. Current from a 120 V load on L1 and one on L2 flow in opposite directions on the neutral and cancel. So the neutral only carries the difference between the two sides. Balanced sides, little neutral current; a straight 240 V load, none at all.
Commercial buildings often get a three-phase service instead — 120/208 V, 277/480 V in the US, or 347/600 V in Canada. Same parts, three lines instead of two; the three-phase lesson covers the voltages.
Neutral and ground: joined once
The neutral is a current-carrying conductor. The bonding (equipment grounding) conductors are not — they only carry current during a fault, long enough to trip the breaker. The two systems are tied together at one point: the main bonding jumper at the service, which is also where the grounding electrode connects. Everywhere downstream they are kept apart. (A separately derived system — the secondary of a dry-type transformer, for one — gets its own bond at its source; your code book gives the details.) If they were joined again in a subpanel or a box, normal neutral current would split and flow on the bonding conductors, conduit and enclosures — metal that people touch.
Worked examples
1. Neutral current on a split-phase panel
- The 120 V loads on L1 add up to 20 A; on L2, 12 A.
- The neutral carries the difference: 20 − 12 = 8 A.
- Move a 4 A load from L1 to L2 and both sides carry 16 A: the neutral current drops to 0 A. That is what balancing a panel does.
2. A 240 V load
- A 4,800 W water heater on 240 V: I = P ÷ V = 4,800 ÷ 240 = 20 A.
- That 20 A goes out on L1 and back on L2. The neutral carries nothing from it — a straight 240 V load does not need one.
- Were it a 120 V heater of the same wattage, it would draw 4,800 ÷ 120 = 40 A. Higher voltage, half the current: why big loads run at 240 V.
Try one: 15 A on L1, 15 A on L2, all 120 V loads
The neutral carries 15 − 15 = 0 A. Perfectly balanced.
Sur le chantier
Tips from the job
- Treat the line side of a main breaker, the meter base and the service conductors as live, always. Only the utility can de-energise them.
- Balance 120 V loads across L1 and L2 as you fill a panel. It keeps the neutral current and the voltage on each side steady.
- Keep the panel schedule current as you go. A panel with “LIGHTS” written on six breakers is a trap for whoever comes next — see reading a panel schedule.
- In a subpanel, check that the bonding screw or strap on the neutral bar is removed (or never installed) before you land anything.
Common mistakes
- Bonding neutral and ground again in a subpanel, putting neutral current on the enclosures and bonding conductors.
- Landing two 120 V circuits that share a neutral on the same line, so the neutral carries the sum instead of the difference.
- Assuming “main off” means the whole panel is dead.
- Mixing up the meter, which measures, with the main disconnect, which switches.
- Sizing anything in a service from memory. Service conductors, main size, electrodes and clearances all come out of your code book.
Check yourself
7 questions. Tap an answer — it is marked straight away and the reason opens under it. Get 80% or better and the lesson is ticked off on the year page.
Not started yet.
-
On a 120/240 V single-phase service, what voltage do you read from L1 to L2?
Answer and why
C. L1 and L2 are the two ends of the transformer’s secondary. The neutral is its centre tap, so each line is 120 V to neutral and the two together are 240 V.
-
Where are the neutral and the equipment ground (bonding) system joined together?
Answer and why
B. The main bonding jumper joins them at the service. Downstream — in a subpanel, a box, a device — they stay separate, or normal neutral current would flow on the bonding conductors and metal parts.
-
L1 is carrying 20 A of 120 V loads and L2 is carrying 12 A of 120 V loads. About how much current is on the neutral?
Answer and why
D. On a split-phase service the two lines are opposite each other, so the neutral carries only the difference: 20 − 12 = 8 A. Balance the two sides and the neutral current falls toward zero.
-
A 4,800 W, 240 V water heater is on a double-pole breaker. What current is on each line, and on the neutral?
Answer and why
A. I = 4,800 ÷ 240 = 20 A, flowing out on L1 and back on L2. A straight 240 V load does not use the neutral at all.
-
What is the main disconnect for?
Answer and why
B. The main breaker or switch is the one place to shut off the whole building’s supply. The meter measures; the main disconnects.
-
In a subpanel fed from the main panel, the neutral bar and the ground bar are…
Answer and why
B. The neutral-to-ground connection is made once, at the service. In a subpanel the neutral bar is isolated from the enclosure and the bonding conductors land on their own bar.
-
Why can you not just tighten a service-entrance lug with the main breaker off?
Answer and why
B. Switching off the main kills the load side. The conductors from the meter to the main’s line terminals are still energised, with the utility’s fault current behind them. Treat them as live until the utility has isolated the service.
Questions fréquentes
What is the difference between a service panel and a subpanel?
The service panel holds (or is right after) the main disconnect, and it is where the neutral and the bonding system are joined by the main bonding jumper. A subpanel is fed from another panel; its neutral bar is isolated from the enclosure, and the bonding conductors land on a separate bar.
Why does the neutral carry less current than the lines?
On a 120/240 V split-phase service, the two lines are 180° apart. Current from a 120 V load on L1 and a 120 V load on L2 flow in opposite directions on the shared neutral, so they partly cancel. The neutral carries the difference between the two sides.
Voir aussi
- Lire le répertoire des circuits d’un panneau
- Continuité des masses ou mise à la terre
- Sous tension, neutre, mise à la terre
- 240 V receptacle wiring — a load that uses L1 and L2 and no neutral.
- Cadenassage, pas à pas
- Grounding and bonding — the first-year lesson this builds on.
- All second year lessons
Vous voyez une erreur sur cette page? Signalez-la
Merci — votre signalement a été envoyé.
L’envoi n’a pas fonctionné. Veuillez réessayer plus tard.
Un petit mot sur les outils qui vous conviennent — par courriel, facultatif
Laissez votre courriel et cochez la case pour un petit mot, au plus toutes les deux semaines, sur les outils, exercices et schémas qui vont avec ce que vous étudiez — ici et sur bentright.com et fieldcalc.net. Une seule liste pour les trois, un clic pour la quitter, et rien n’est envoyé avant que vous confirmiez depuis votre boîte de réception.