Troisième année Lesson 11 of 13 · about 12 min
Commercial wiring methods
What you’ll learn
- The main raceways and cables on a commercial or industrial job, and the job each is good at.
- How the location — wet, corrosive, damage, heat, vibration — steers the choice.
- The questions to ask the code book and the specification before a run goes in.
- A little pulling physics: why bends multiply tension.
Before this: Conduit bending basics · Second year
A wiring method is the way conductors get from one place to another and stay protected: pulled into a raceway, built into a cable assembly, laid in tray, or carried as bars in a busway. On a house it is mostly one kind of cable; on a commercial or industrial job you will use half a dozen methods in one building, each where it suits. What is permitted where is your code book’s call, and what is required on this job is the specification’s. This lesson is about why each one exists.
Raceways: the pipe first, the wire later
| Method | Good at | Watch for |
|---|---|---|
| EMT (thin-wall steel) | Fast, light, bends by hand; the default indoor commercial raceway | Physical damage, wet or corrosive places; set-screw vs compression fittings |
| Rigid steel (RMC) / IMC | Physical protection, outdoors, some hazardous locations; threaded joints | Heavy, slow, needs threading; corrosion in some soils |
| Rigid PVC | Underground, in slabs, wet and corrosive areas; no rust | Big thermal expansion; not a bonding path; sunlight and damage ratings |
| Flexible metal conduit | Short runs to equipment that moves or vibrates; awkward spaces | Bonding through it is limited; dry locations |
| Liquidtight flex | Motors and equipment in wet, oily or washdown areas | Fittings must match; bonding rules for its length |
Cables, tray and busway
Armoured cable — AC90 and Teck90 in Canada, AC and MC cable in the US — puts the conductors, usually a bonding conductor, and a metal armour into one assembly. It goes in far faster than pipe and wire, handles vibration, and Teck’s jacketed armour suits industrial and tray work. Cable tray is an open ladder or trough that supports many cables at once; cables are laid in, not pulled, so adding a circuit later is easy — but only tray-rated cables go in it. Busway is copper or aluminum bars in a housing for large currents: a service riser, or a plug-in run down a factory floor that machines tap off anywhere.
The questions to ask before a run goes in
- Where is it? Dry, damp, wet, corrosive, hot, cold, exposed to damage, hazardous, a return-air plenum, underground, in concrete?
- What does the specification say? The owner may require more than the minimum — steel instead of cable, particular fittings.
- What does the code book permit there? For this method in this location and occupancy — and the conditions attached to it.
- How is it bonded? Is the raceway or armour the bonding path, or does a bonding conductor go with it?
- How will it be supported, pulled and terminated? Supports, bends, pull points, fittings — the numbers are in the book and the maker’s instructions.
Worked: why bends multiply pulling tension (practice numbers)
- Three conductors weighing 0.5 lb/ft each (a practice weight — the real one is on the cable data sheet): 1.5 lb/ft in total.
- A 200 ft straight horizontal run with a friction coefficient of 0.5: tension = weight × length × friction = 1.5 × 200 × 0.5 = 150 lb (about 667 N).
- Through a 90° bend, tension multiplies by eμθ, θ in radians: 90° = 1.571 rad, so e0.5 × 1.571 = e0.785 = 2.19.
- Tension leaving the bend = 150 × 2.19 = about 329 lb (about 1,460 N). A second 90° would multiply it by 2.19 again.
- So feed from the end nearest the bends, where the tension is still small, and compare against the cable maker’s maximum pulling tension.
Sur le chantier
Tips
- Read the wiring-methods section of the specification before the first stick goes up.
- Flag every change of location type on a run — indoor to outdoor, dry to wet — because the method or fittings usually change there too.
- Pull PVC runs with expansion in mind: leave room and use expansion fittings on long exposed runs.
- Plan pull points so no section collects too many bends.
- Keep armour and raceway joints tight — they are often part of the fault path.
Common mistakes
- Using EMT set-screw fittings where the location calls for raintight or compression.
- Running a cable type in tray that is not rated for tray.
- Forgetting the bonding conductor in PVC.
- Rigid conduit straight onto a vibrating motor.
- Choosing the method by habit instead of by location, spec and code book.
Check yourself
-
1.Why is the last few feet (or metre) to a motor usually flexible or liquidtight flexible conduit rather than rigid?
Motors vibrate and get moved to tension belts or align couplings. A rigid connection would fatigue and crack. Liquidtight versions add protection where there is water, oil or washdown. Whether flex can serve as the bonding path, and how long it may be, are questions for your code book.
-
2.Where is rigid PVC conduit most at home?
PVC does not corrode, so it shines underground, in concrete and in corrosive areas. It is not conductive, so a separate bonding conductor is always pulled with it, and it expands and contracts a lot with temperature — long exposed runs need expansion fittings.
-
3.You pull cable through a raceway with a straight-run tension of 150 lb (667 N) arriving at a 90° bend. With a friction coefficient of 0.5, roughly what is the tension leaving the bend?
Tension multiplies through a bend by e^(μθ), with θ in radians. For 90° (1.571 rad) and μ = 0.5, e^0.785 = 2.19, so 150 × 2.19 ≈ 329 lb (about 1,460 N). Bends multiply — which is why you pull from the end nearest the bends when you can.
-
4.What is a main advantage of cable tray in an industrial plant?
Tray is an open support system: cables are laid in, not pulled, and adding a circuit later is easy. Only cable types rated for tray may be used, and fill, spacing and bonding of the tray follow the code book.
-
5.Teck (in Canada) and MC cable (in the US) are both…
Both are armoured cable assemblies: the conductors, often a bonding conductor, and a metal armour (Teck adds an outer jacket). They go in fast and handle tray and industrial use. Which uses they are allowed, and whether the armour counts as a bonding path, depend on the product and your code book.
-
6.What is busway (bus duct) typically used for?
Busway is rigid copper or aluminum bars in a metal housing, rated for large currents. Plug-in busway lets machines be tapped off anywhere along its length, which suits factories that rearrange equipment.
-
7.Before choosing a wiring method for a run, which question is NOT one you should be asking?
Every run starts with the location, the occupancy, what the code permits there, and what the specification requires. "Same as last time" is how the wrong method ends up in a return-air plenum or a corrosive room.
Questions fréquentes
EMT or rigid — how do I know which one?
Start with the spec and drawings; the engineer usually decides. Behind that decision is the location: EMT is light, fast and fine for most dry indoor work; rigid (RMC) and intermediate (IMC) steel are for physical damage, outdoors, some hazardous locations and where the wall thickness matters. Where each is permitted is in your code book.
Is AC90 the same as MC?
They are close cousins. AC90 (Canada) and AC / MC cable (US) are all armoured cable assemblies with the conductors inside, but the armour construction and whether the armour counts as a bonding path differ between products. Read the cable marking and check your own code book for its uses.
Why does the spec book matter if the code book already sets the rules?
The code sets the minimum that is allowed. The specification tells you what this owner is paying for, which is often more — EMT instead of cable, steel instead of PVC, particular fittings or colours. You install to whichever is stricter, and the spec is part of your contract.
Voir aussi
- Les bases du cintrage de conduits
- Fittings index — the pieces each method uses
- Reading commercial and industrial prints
- Grounding and bonding as a system — when the raceway is the bonding path
- Hazardous locations: the ideas
Vous voyez une erreur sur cette page? Signalez-la
Merci — votre signalement a été envoyé.
L’envoi n’a pas fonctionné. Veuillez réessayer plus tard.
Un petit mot sur les outils qui vous conviennent — par courriel, facultatif
Laissez votre courriel et cochez la case pour un petit mot, au plus toutes les deux semaines, sur les outils, exercices et schémas qui vont avec ce que vous étudiez — ici et sur bentright.com et fieldcalc.net. Une seule liste pour les trois, un clic pour la quitter, et rien n’est envoyé avant que vous confirmiez depuis votre boîte de réception.